WORK FLOW CHART FOR INTERNAL & EXTERNAL DEVELOPMENT WORK AND COMMON AMENITIES OF SPARSH LIFE CITY, RAIPUR

S.N. Item Estimated Starting Date Estimated Completion Date Actual Completion Date Status
Total Project 10-12-2017 10-06-2020
1. Cutting,leveling,dressing,supplying,laying and compaction and moorum 10-12-2017 15-06-2018
2. supplying,laying and compaction of WMM 03-02-2018 15-07-2018
3. Cement concrete work 06-03-2018 20-07-2018
4. Boundary Wall 06-03-2018 20-07-2018
5. Sumpwell with pump 20-01-2018 30-06-2019
6. Septic Tank 01-01-2019 30-06-2019
7. Swerage line with inspection chambers, cutting, filling and compacting all complete 12-12-2018 31-10-2019
8. HDPE water supply line 10-11-2019 28-02-2020
9. Paver work 20-11-2019 31-03-2019
10. Main Gate 15-02-2018 30-07-2018
11. Landscape work 01-07-2018 31-03-2020
12. Temple 15-06-2018 30-12-2018
13. Children Play Area 01-01-2019 30-06-2019
14. Plot marking with pole 09-07-2018 30-12-2018
15. Electrification work 01-01-2019 31-12-2019
16. Rain water harvesting 01-01-2020 31-03-2020
17. Social amenities(skating,open gym,open amphitheater) 01-06-2019 31-12-2019
18. Club house(indoor games, waiting lounge, swimming pool with changing room and common toilet) 01-07-2018 31-03-2020